Two 1990s-era basin liners at the city's wastewater plants are worn out and have been patched repeatedly. A $724,405 contract replaces them, funded from the sewer budget.
At a glance
- Total mentions
- 6
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Nov 9, 2026.
Impact analysis
$724,405 including contingency, paid from the sewer budget.
All city sewer customers, through more reliable treatment plant operation.
Mentions & discussions (6)
City Council โ November 9, 2026
Two 1990s-era basin liners at the city's wastewater plants are worn out and have been patched repeatedly. A $724,405 contract replaces them, funded from the sewer budget.
City Council โ June 22, 2026
The city is locking in a low-interest state loan to fund critical upgrades at its wastewater plants, including digester lid replacement and SCADA system modernizations.
City Council โ June 8, 2026
Council authorized a low-interest state loan and contracts over $3 million to replace a failing digester lid and modernize computer control systems at the wastewater plants.
Council โ May 18, 2026
The city awarded an $829,916 contract for sewer pipe lining and manhole rehabilitation, leveraging a $1.5 million state grant.
Council โ March 9, 2026
Anderson is securing a $2.19 million low-interest loan to replace an aging anaerobic digester lid at the Rocky River plant and upgrade computer control systems at both wastewater plants.
Council โ February 23, 2026
The city established a formal agreement with Homeland Park to regulate industrial wastewater discharges and meet state environmental rules.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Anderson
What the council decided, in plain English โ one email a week.
Free. Unsubscribe with one click any time. We never sell your email.