Fire Station #1 Renovations
Summary
A $699,444 renovation contract for the 1984-built fire station was tabled after Scallate questioned the bay expansion and security entry line items. Roof, windows and solar panel work are the pieces everyone agrees on; the rest awaits renegotiation.
At a glance
- Total mentions
- 1
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Nov 10, 2026.
Impact analysis
$800,000 budgeted from the Capital Projects Fund; contract tabled to potentially trim costs.
Firefighters and residents if the aging station is brought up to standard.
Deferred maintenance continues to worsen conditions at the 1984 station.
Mentions & discussions (1)