High PriorityWater Utilitiesopen

Marina Day Dock Repairs and Day Dock Permitting

Summary

City staff outlined a three-month permitting process for the Day Dock and Marina Day Dock, damaged by Hurricane Helene. Both docks will go out for concurrent RFPs with a target completion goal around July 1 ahead of the Water Festival.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Jan 12, 2026.

Impact analysis

💰Financial impact

Project costs will be partially offset by insurance coverage and potential FEMA mitigation funds.

✅Who benefits

Boaters, tourists, and local charter operators will benefit from restored and expanded dock capacity.

Mentions & discussions (1)

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Beaufort

What the council decided, in plain English — one email a week.