Stuart Point Pathway Project contract

Summary

A long-delayed two-mile pathway connecting Stuart Point Road to three schools finally got its construction contract — delays stemmed from extensive right-of-way acquisitions, District 5's Howard noted.

At a glance

Total mentions
1
Last 30 days
1

Discussed at 1 meeting in the last 60 days; most recently Nov 16, 2026.

Impact analysis

💰Financial impact

$1,978,701.50 total, about 2% under the engineer's estimate, including a $200,000 CDBG grant.

✅Who benefits

Stuart Point residents and students gain a safe walking route to three schools.