Foster wastewater treatment plant transfer
Summary
The county's aging Foster plant — a 1960s-era lagoon package plant serving an industrial area — costs $75,000-$92,000 a year to run and needs an estimated $440,000 in pipe rehabilitation. Council wants the water and sewer district to take it over and okayed restarting negotiations.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Apr 27, 2026.
Impact analysis
Could stop roughly $75,000-$92,000 a year in operating costs plus a major pipe-repair bill.
County taxpayers stop funding a plant that serves only the Foster industrial area.