Naming of the Williford L. Faile Detention Center
Summary
The new detention center is 74% complete at about $58 million spent against a $90 million budget, but the schedule slipped about three months — substantial completion now March 2027 and first inmates July 2027. New state regs may allow more beds than planned.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Oct 12, 2026.
Impact analysis
Budget holds at $90 million with $58 million spent and contingency holding well.
The Sheriff's Office, detention staff, and inmates gain a modern facility with day-room daylight.
None identified.
Mentions & discussions (2)
Lancaster County Council - Oct 12, 2026
The new detention center is 74% complete at about $58 million spent against a $90 million budget, but the schedule slipped about three months — substantial completion now March 2027 and first inmates July 2027. New state regs may allow more beds than planned.
Lancaster County Council - Sep 14, 2026
The new detention center on Highway 9 will carry the name of the late sheriff — a 32-year department veteran, 13-year sheriff, and Order of the Palmetto recipient.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Lancaster County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.