14 Mile Creek Gravity Trunk Sewer Project
Summary
The town's sewer system is getting major attention: upgrades to the Mill Stream Station that handles 90–95% of sewer flow, hydraulic modeling, and system-wide inspections. Long-term, the town must expand sewer treatment capacity in Cayce, and a Professional Engineering Report will define scope and costs.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Last discussed May 4, 2026.
Impact analysis
Sewer treatment from the City of Cayce is budgeted around $5.3 million in FY 26, and roughly $59 million in future capital spending is projected, possibly funded by bonds and rate adjustments.
Sewer customers benefit from improved reliability and long-term capacity for growth.
Property owners along the route who may face condemnation if negotiations fail.
Mentions & discussions (3)
1 - Town Council - May 4, 2026
The town can now buy — or condemn, if needed — property rights it needs for a gravity sewer line project.
1 - Town Council (Work) - Apr 20, 2026
The town's sewer main is in good shape but can't handle future growth and heavy-rain flows. A parallel sewer line is planned — about 18 months of easement negotiations (with possible condemnation) across roughly 117 parcels, then 18 months of construction.
1 - Town Council - Mar 23, 2026
The town's sewer system is getting major attention: upgrades to the Mill Stream Station that handles 90–95% of sewer flow, hydraulic modeling, and system-wide inspections. Long-term, the town must expand sewer treatment capacity in Cayce, and a Professional Engineering Report will define scope and costs.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Lexington
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.