Stadium Project Agreement Amendment No. 2
Summary
The stadium's guaranteed maximum price rose from about $32 million to roughly $37.8 million to finish the team store, locker rooms, suites, press box and other spaces. The leaseholder — not the city — pays the increase.
At a glance
- Total mentions
- 2
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Nov 16, 2026.
Impact analysis
No direct cost to the city — the leaseholder covers the $4.8+ million increase.
Fans, event-goers, and nearby businesses that will benefit from a fully finished stadium.
Drivers and nearby residents who are about to deal with major game-day traffic headaches and construction noise.
Mentions & discussions (3)
City Council Meeting - - City of Mauldin, SC — November 16, 2026
The stadium's guaranteed maximum price rose from about $32 million to roughly $37.8 million to finish the team store, locker rooms, suites, press box and other spaces. The leaseholder — not the city — pays the increase.
Committee Meetings and Special Called City Council Meeting - - City of Mauldin, SC — September 8, 2026
The city finalized changes to its Bridgeway Station stadium deal: Hat Trick Properties takes over Greenville Pro Soccer's role, the term is restated at 30 years, and the club can use temporary facilities until the stadium opens. The city also approved an easement agreement with CenterPlace.
Design revealed for pro soccer stadium in Mauldin as construction begins
Design revealed for pro soccer stadium in Mauldin as construction begins Greenville Journal
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Mauldin
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.