Dovre and Alhambra basins drainage improvements
Summary
A $373,900 change order expands Thomas & Hutton's role to full design and permitting for basin drainage upgrades, including bigger pipe capacity and offline improvements to capture more water. Permitting runs to September 2027; construction starts in 2028.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Jul 6, 2026.
Impact analysis
$373,900.00 in change-order cost, backed by a separate grant funding source.
Residents around the Alhambra and Dovre basins who face drainage capacity limits.