Broadway Street septic permit appeal
The state approved six septic tank permits for Broadway Street lots even though public water and sewer are available to four of them. MPW appealed, worried septic systems could add bacteria to already-impaired Shem Creek. The permits haven't been rescinded yet.
Gramling Aquifer deep well exploration
MPW drilled 3,010 feet into the Gramling Aquifer under Highway 17 North and hit promising water-bearing sand. If testing over the next few months pans out, it could become a major new drinking water source — Council Member Chapman suggested enough for the next 100 years.
Septic permit appeal on Broadway Street
The state approved six septic tank permits for Broadway Street lots even though public water and sewer are available to four of them. MPW appealed, worried septic systems could add bacteria to already-impaired Shem Creek. The permits haven't been rescinded yet.
Shem Creek Maintenance and Dredging
The board reviewed and approved expansion plans for the Shem Creek Boat Landing, ensuring local neighbor drainage concerns were properly addressed by county project managers.
Edwards Park Drainage Basin Project FEMA grant
The Town's $7 million flood drainage project at Edwards Park is designed and shovel-ready, but still waiting on FEMA money. The federal BRIC program was eliminated then reinstated, so the Town switched to a Hurricane Helene hazard mitigation grant with a longer timeline — a FEMA decision is now expected within 18 months.
FY 2026 stormwater and infrastructure project schedule
The town owns 21 wet detention ponds, 7 with ongoing problems. Staff outlined buffer plantings, contracted water quality care, and a cheap "no-mow buffer" starter approach — and confirmed current funding is enough to begin. Better pond care can head off multi-million-dollar dredging bills that otherwise land on HOAs and homeowners.
Flooding relief at Ferry Street and Pitt Street
This intersection floods so badly staff have had to wade in and clear debris by hand. A new curb inlet, repaving and a crosswalk should cut blockages and make the crossing safer for walkers.
Mill Tract Basin stormwater improvements
The town owns 19 of roughly 972 wet ponds in Mount Pleasant. Staff showed cheap upgrades — native plant buffers and floating wetlands ($10,000–$20,000 each) — and members want the town to upgrade all its own ponds and lead by example.
Future utility undergrounding program
Members carefully avoided framing tree planting money as competing with burying power lines — a fight that could tank support. The recommendation now backs both, leaving budget calls to council; the Public Services Committee is working on a structured undergrounding program.