Development

Data center

Summary not yet generated for this topic.

Community sentiment

Concerned (1)

At a glance

Public comments
1
Last 30 days
0

Last discussed Jul 15, 2026.

Public comments (35)

SupportiveVicky BilkaJul 15, 2026

Longtime data center watchdog returned to show continued support, citing national drought data up 86.5%, Newberry County in moderate drought, and Spartanburg County's new lawsuit against Valara Holdings over unpermitted gas generation capacity.

Newberry County Council - Work Session — July 15, 2026 · 1:53:29 →
SupportiveUnidentified Resident (Ms. Moss)Jul 15, 2026

Lives a mile and a half from the proposed data center site; urged the council to pass the moratorium, take time on research, and make it permanent or extend it if the county lacks information, citing noise and nearby families.

Newberry County Council - Work Session — July 15, 2026 · 1:57:01 →
SupportiveLeslie Lander OrrJun 17, 2026

Supported the moratorium, saying the state won't act so the county must protect itself.

Newberry County Council - Work Session — June 17, 2026 · 2:04:32 →
OpposedKaren JohnsonJun 17, 2026

Urged council to go beyond a moratorium and ban data centers outright, calling it true leadership.

Newberry County Council - Work Session — June 17, 2026 · 2:05:46 →
OpposedVicky BilkaJun 17, 2026

Asked council for a permanent moratorium, cited water use concerns and called for independent studies of data center impacts.

Newberry County Council - Work Session — June 17, 2026 · 2:07:49 →
OpposedJames J. ZybriJun 17, 2026

Demanded transparency, saying the data center project appeared to be sneaked through under a code name.

Newberry County Council - Work Session — June 17, 2026 · 2:11:01 →
OpposedWilliam DuPreeJun 17, 2026

A former Air Force network operations worker, he warned data centers promise jobs but deliver noise, road damage, and huge water and power use.

Newberry County Council - Work Session — June 17, 2026 · 2:13:37 →
OpposedDeborah DuPuyJun 17, 2026

Said the data center is bad for people and agriculture and demanded transparency over code names.

Newberry County Council - Work Session — June 17, 2026 · 2:15:28 →
OpposedConstance LavelleJun 17, 2026

Cited economic research and EPA statements arguing data centers don't pass a cost-benefit test and pollute; asked for her research to be received.

Newberry County Council - Work Session — June 17, 2026 · 2:16:01 →
OpposedAbby GriffinJun 3, 2026

A part-time resident and college student opposed the data center, citing water and power consumption and AI's harm to students and careers.

Newberry County Council — June 3, 2026 · 1:09:16 →
OpposedAmanda MossJun 3, 2026

A resident living within two miles of the site urged a no vote, citing pollution, nearby schools, rising utility bills, and harm to wildlife.

Newberry County Council — June 3, 2026 · 1:12:01 →
ConcernedLily HunterJun 3, 2026

Asked the county to verify infrastructure capacity, emergency access, and to retain its own independent expert to oversee construction plans.

Newberry County Council — June 3, 2026 · 1:14:35 →
OpposedJulia PinkneyJun 3, 2026

Asked the council to adopt a temporary moratorium on data centers until independent environmental and infrastructure studies and real public engagement are done; noted a 1,500-signature petition.

Newberry County Council — June 3, 2026 · 1:16:05 →
OpposedUnidentified ResidentJun 3, 2026

Announced delivery of a 1,529-signature petition and posed written questions about other data center projects, future project evaluation, and how the council evaluated Project LTR.

Newberry County Council — June 3, 2026 · 1:19:04 →
OpposedEmily PooleJun 3, 2026

An attorney with the SC Environmental Law Project urged the council not to proceed until project details — water, energy, noise, stormwater, tax incentives — are disclosed, citing the Spartanburg Valera expansion as a cautionary example.

Newberry County Council — June 3, 2026 · 1:24:50 →
OpposedUnidentified ResidentJun 3, 2026

Accused the council of betraying public trust by voting on the project under a code name, and demanded the ordinance be killed and put to a binding public referendum.

Newberry County Council — June 3, 2026 · 1:28:04 →
OpposedCharlie StuffJun 3, 2026

Said he's shifted his position and would like data centers banned from Newberry County entirely.

Newberry County Council — June 3, 2026 · 1:30:43 →
OpposedVicky BilcomJun 3, 2026

A Chapin transplant living 2.7 miles from the site described well reliance, nearby schools, ground heating from data centers, and the nearby fault line, and asked each member how close they live to the project.

Newberry County Council — June 3, 2026 · 1:32:43 →
OpposedSteve McKeanJun 3, 2026

Argued the data center's water demand would irreparably harm the county's farming, livestock, and timber industries, which depend on balanced water supplies.

Newberry County Council — June 3, 2026 · 1:36:27 →
OpposedUnidentified ResidentJun 3, 2026

A self-described 80-year-old veteran of government warned that data centers carry externalities — noise, heat, pollution, infrastructure damage — that corporations historically don't pay for.

Newberry County Council — June 3, 2026 · 1:39:33 →
OpposedKaren JohnsonJun 3, 2026

A relative newcomer said the county's beauty and peacefulness drew her family here and invoked stewardship of the land in opposing the data center.

Newberry County Council — June 3, 2026 · 1:49:33 →
OpposedUnidentified ResidentJun 3, 2026

A manufacturing veteran used 'five whys' to question why Newberry, urged the council to bring the public real numbers instead of closed-door decisions.

Newberry County Council — June 3, 2026 · 1:51:04 →
OpposedUnidentified ResidentJun 3, 2026

Noted AI data centers employ only 20-50 people and asked who gets water priority during a drought — families and farmers or a contractually protected data center.

Newberry County Council — June 3, 2026 · 1:53:05 →
OpposedAnthony CaldwellJun 3, 2026

Acknowledged some data center benefits but said utility costs, water disposal, few permanent jobs, and the lack of transparency are red flags for the community.

Newberry County Council — June 3, 2026 · 1:54:40 →
OpposedBecky BolandJun 3, 2026

One mile from the site, she said residents are tired of fighting to keep the area rural, defended the audience's applause, and urged the community to stay engaged.

Newberry County Council — June 3, 2026 · 1:59:45 →
OpposedUnidentified ResidentJun 3, 2026

A soon-to-be-80-year-old businessman criticized the council for serving corporate interests over citizens, cited farmland statistics, and warned incumbent councils have been voted out over data centers.

Newberry County Council — June 3, 2026 · 2:02:42 →
OpposedUnidentified ResidentJun 3, 2026

Claimed data center vibration and noise endanger pacemaker patients and fetuses, threatened an investigation if the project proceeds, and said Lake Murray is not for sale.

Newberry County Council — June 3, 2026 · 2:06:40 →
OpposedCaseyJun 3, 2026

Reading notes for Fran Smith, raised concerns about the Dominion/NextEra (BlackRock) merger, local workers' qualifications, environmental studies, and vowed to sell her land if the project proceeds.

Newberry County Council — June 3, 2026 · 2:11:09 →
OpposedMegan SesslerJun 3, 2026

A farmer detailed water use (up to 5 million gallons/day), power demand, permanent loss of farmland, diesel generator pollution, and asked the council to vote no and ban data centers.

Newberry County Council — June 3, 2026 · 2:13:32 →
ConcernedTracy CliffordMay 20, 2026

Signed up to comment on the data center, but the item was not on the agenda.

Newberry County Council - Work Session — May 20, 2026 · 1:56:15 →
ConcernedStephen McKeanMay 6, 2026

A former planning commissioner urged council to confirm where water for the proposed data center would come from, warning that farmland and well water for some 24,000 residents can't be replaced once diverted.

Newberry County Council - Work Session — May 6, 2026 · 2:13:22 →
OpposedJamie JohnsonMay 6, 2026

A farmer objected that the May 18 data center panel includes only pro-data-center speakers and quoted the administrator saying no opponents would be included, demanding both sides be presented.

Newberry County Council - Work Session — May 6, 2026 · 2:18:07 →
OpposedCharlie StuckMay 6, 2026

Stuck said most people who oppose the data center won't speak publicly, cited national polls showing more opposition than support, and echoed calls for the county to present both sides.

Newberry County Council - Work Session — May 6, 2026 · 2:22:33 →
ConcernedJulia PinkneyMay 6, 2026

Pinkney asked that the information session include environmental analysis of water use and electricity, and questioned who pays for infrastructure and whether tax breaks would erode the benefit.

Newberry County Council - Work Session — May 6, 2026 · 2:25:07 →
OpposedBarry LakeMay 6, 2026

Lake urged council not to sign NDAs, cited state Senate testimony on speculative data center proposals and grid strain, and called the May 18 meeting a continuation of a process that lacks transparency.

Newberry County Council - Work Session — May 6, 2026 · 2:27:02 →