Mid-Carolina Commerce Park Phase 3B roadway project
Summary
The county wants to finish the commerce park's back road and build a 300,000-square-foot pad so the site is truly shovel-ready for industrial prospects. A $3 million state grant covers most of the $4.25 million cost, leaving about $1 million for the county.
At a glance
- Total mentions
- 5
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Nov 4, 2026.
Impact analysis
About $1 million of county money would go into the project after the state grant.
Future industrial prospects and county economic development recruiting — and ultimately local jobs.
Mentions & discussions (5)
Newberry County Council - Work Session — November 4, 2026
Roadway clearing and pad-site work is moving fast at the commerce park, and the county has formally asked the SC Department of Commerce for excess grant funds to build a 150,000-square-foot engineered pad. A stormwater detention basin is next.
Newberry County Council - Work Session — September 16, 2026
A new 1,250-foot road extension and 300,000-square-foot graded pad will give the county its first marketable shovel-ready industrial site in years, mostly paid by a $3 million state grant.
Newberry County Council - Work Session — July 15, 2026
Bid ads go out around July 23 for the Phase 3B roadway extension and pad site, funded in part by a $2.5 million site enhancement grant, with council approval expected in September.
Newberry County Council - Work Session — May 6, 2026
The county wants to finish the commerce park's back road and build a 300,000-square-foot pad so the site is truly shovel-ready for industrial prospects. A $3 million state grant covers most of the $4.25 million cost, leaving about $1 million for the county.
Newberry County Council - Work Session — January 7, 2026
The Boscos Way extension in the industrial park should finish March 20, and Mid-Carolina Commerce Park Phase 3B water/sewer is on track for July 10. The county also won a $3 million state grant to extend the park road and create a buildable 300,000-square-foot site.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Newberry County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.