Lauret Tract road completion deadline
Summary
The developer of the huge Lauret Tract subdivision got 12 more months (plus a 4-month cure period) to pave Long Bay Road, which was due in September 2025. Mayor Baldwin pushed hard for a faster schedule, citing public safety; the developer says a bond and building-permit holdbacks give the city real leverage now.
At a glance
- Total mentions
- 2
- Last 30 days
- 1
Last discussed Feb 16, 2026.
Impact analysis
The city takes on maintenance of the county road segment once built; the developer must post a financial guarantee.
Residents of the development and surrounding areas who need better ingress/egress and emergency access.
Mentions & discussions (2)
Horry County has seen delays in some of its RIDE road projects. Here’s why
Aerial photos show the progress of road construction in the downtown area of Myrtle Beach, S.C. The South Carolina Department of Transportation is working to realign U.S. 501 to improve traffic flow to downtown...
City Council - Feb 16, 2026
The developer of the huge Lauret Tract subdivision got 12 more months (plus a 4-month cure period) to pave Long Bay Road, which was due in September 2025. Mayor Baldwin pushed hard for a faster schedule, citing public safety; the developer says a bond and building-permit holdbacks give the city real leverage now.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for North Myrtle Beach
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.