Paris Avenue streetscape nearing completion

Summary

The streetscape project is underway and finishes around September 3. Paris Avenue stays open the whole time, but expect traffic impacts — council is urging everyone to keep supporting the businesses along the route.

At a glance

Total mentions
11
Last 30 days
2

Discussed at 3 meetings in the last 60 days; most recently Nov 4, 2026.

Impact analysis

💰Financial impact

Grant-funded project; a time extension was approved pushing substantial completion to October 9.

✅Who benefits

Everyone who'll enjoy the finished streetscape — and businesses if shoppers keep coming during construction.

⚠️Who could be affected

Paris Avenue businesses dealing with construction traffic and parking changes through the summer.

Mentions & discussions (11)

MeetingNov 4, 2026

Town Council - Nov 4, 2026

The streetscape project is almost done — final milling and asphalt require closing Paris Avenue Sunday through Tuesday next week (Wednesday as a backup). Saturday stays open so the Holiday Market and Oyster Roast aren't affected.

MeetingOct 15, 2026

Town Council - Oct 15, 2026

The town's biggest-ever project is weeks from done: wider sidewalks, benches, golf cart parking, slower traffic, and a major stormwater overhaul beneath it. Officials stressed it was shaped by a 2023 public charrette and is 90% paid for by a state CDBG grant, costing the town only about 10% of the million-plus-dollar price.

MeetingOct 7, 2026

Town Council - Oct 7, 2026

New asphalt is down and crosswalks and striping come next; two-way traffic should return early next week with Dominion installing lights Monday.

MeetingSep 2, 2026

Town Council - Sep 2, 2026

Phase 1 (east side) gets its first asphalt lift this week with substantial completion October 9; Phase 2 (west side) follows. Crews start trench drains and irrigation tomorrow, with more weekend work planned.

The Island News (Port Royal tag)Aug 20, 2026

Drainage project update: Craven Street re-opens for traffic

Temporary base paving and striping on Craven Street was completed earlier this week, allowing the street to be re-opened to traffic.

MeetingAug 12, 2026approved

Town Council - Aug 12, 2026

Staff reported pressure-release valve work on the slide pads, Savannah Artscape progress on the streetscape, 15 new light fixtures arriving August 16, and a Beaufort-Jasper Water & Sewer shutdown the next evening for a fire hydrant grant tie-in.

MeetingAug 5, 2026

Town Council - Aug 5, 2026

Phase one of the $15-17 million Paris Avenue upgrade is in month five of a six-month build, with sidewalks and pavers going in now and completion expected in early September. New stormwater lines, underground utilities, lighting, and a mosaic are part of the plan.

MeetingJul 1, 2026

Town Council - Jul 1, 2026

The CDBG-funded Paris Avenue project is nearly on schedule for a September 3 finish, but a restaurant owner says his business is down 40% and asked for hospitality tax relief. Council didn't act but heard him out.

MeetingJun 3, 2026

Town Council - Jun 3, 2026

Phase 1 stormwater work on Paris Avenue is on track for a September 3 completion. The splash pad should open around June 10, and the Villages drainage project is 95 percent done.

MeetingApr 1, 2026

Town Council - Apr 1, 2026

The streetscape grant project is on track for September completion, and council urged residents to keep supporting the shops and restaurants along Paris Avenue during construction.

MeetingMar 4, 2026

Town Council - Mar 4, 2026

The streetscape project is underway and finishes around September 3. Paris Avenue stays open the whole time, but expect traffic impacts — council is urging everyone to keep supporting the businesses along the route.

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Port Royal

What the council decided, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.