Spartanburg County · week of November 1, 2026

Council approves Second reading — Numara/Valara development agreement (4000 S. Pine Street), 3–2

Summarized from the official meeting transcript — every claim links to the moment it was said. How we make this

What changed in Spartanburg County

  • First reading — Ordinance prohibiting parking, stopping, standing on certain county roads

    0 yes, 0 no

    Watch this moment →
  • First reading — Joint Industrial and Business Park agreement (Technology Park–Cherokee County)

    0 yes, 0 no

    Watch this moment →
  • First reading — Amendment removing Spartanburg property from 2002 Union County joint industrial park

    0 yes, 0 no

    Watch this moment →
  • First reading — Amendment removing Spartanburg property from 2009 Cherokee County joint industrial park

    0 yes, 0 no

    Watch this moment →
  • First reading — Joint Industrial and Business Park agreement (Technology Park–Union County)

    0 yes, 0 no

    Watch this moment →
  • First reading — Dissolving the 2006 Union County joint industrial park

    0 yes, 0 no

    Watch this moment →
  • First reading — Amended and restated ground lease to SB Acquisitions, LLC

    0 yes, 0 no

    Watch this moment →
  • Second reading — Numara/Valara development agreement (4000 S. Pine Street)

    3 yes, 2 no

    Watch this moment →
  • Second reading — AIB CLT1 development agreement (389 Tyger River Industrial Drive)

    0 yes, 0 no

    Watch this moment →
  • Second reading — 300 Jones Road Associates development agreement (430 Jones Road)

    0 yes, 0 no

    Watch this moment →

Development activity

  • 2910 E Main Street Commercial Subdivision

    2910 E Main Street, Spartanburg, SC

    A major site plan for a townhome development at 2910 E.

    Discussed — no decision yet

    Track this project →
  • High-Performance Computing Center Development Agreement

    4000 S. Pine Street, Spartanburg, SC 29302

    A development agreement for a high-performance computing center at 4000 S.

    still pending

    Track this project →
  • SB Acquisitions Ground Lease

    Parcels 5-24-00-024.00; 5-24-00-094.00; 5-24-00-081.00; 5-28-00-010.01; 5-24-00-099.00

    An amended and restated ground lease covering five county parcels would be granted to SB Acquisitions, LLC.

    Discussed — no decision yet

    Track this project →
  • 300 Jones Road Data Center

    at or near 430 Jones Road

    A data center on roughly 137 acres at the former RR Donnelley plant site, capped at 65 IT megawatts, grid-powered, with $1.5 billion anticipated investment, at least 25 jobs, and $9 million in community benefit payments.

    still under-review

    Track this project →
  • Numara & Valara High-Performance Computing Center

    4000 S. Pine Street, Spartanburg, SC 29302

    A roughly 293-acre high-performance computing center with a 457-megawatt on-site natural gas power component, advanced on second reading 3-2 with Council Member Abusaft voting no over broken environmental promises and litigation threats.

    still under-review

    Track this project →
  • 300 Jones Road Associates LLC Development Agreement

    430 Jones Road

    A development agreement for a data center on about 137 acres at or near 430 Jones Road, with a public hearing and possible second reading Tuesday.

    still pending

    Track this project →
  • AIB CLT1 Data Center

    389 Tyger River Industrial Drive

    A conversion of an existing data center site to a single building capped at 50 IT megawatts (65-megawatt facility maximum), grid-powered with only emergency backup generation, with about $1.2 billion in anticipated investment and at least 28 jobs.

    still under-review

    Track this project →

Also discussed

  • Data Center Development Moratorium

    The county is starting to plan how its Performance Zoning Ordinance would handle data centers. No vote is requested yet, but this sets the stage for how — and where — data centers could be built in Spartanburg County.

    What it means: Ultimately residents and county leaders who would gain clear rules before data center proposals arrive.

    Raised 2 times this week

    Follow this issue →
  • Joint industrial park agreements with Cherokee and Union counties

    Council created a new technology park with Cherokee County and one with Union County, amended two older joint park agreements to drop Spartanburg property, and dissolved a 2006 park agreement with Union County. These housekeeping measures reshape where multi-county industrial development incentives apply.

    What it means: Residents and the county benefit from clarified industrial park boundaries and refreshed economic development tools.

    Follow this issue →
  • Roadside parking ban in unincorporated areas

    First reading passed of an ordinance banning parking, stopping and standing along certain county roads — a safety measure that will affect drivers and residents along the designated roads once finalized.

    What it means: Motorists and residents along the affected roads gain safer, clearer travel lanes.

    Follow this issue →
  • Zoning permit extensions

    Two projects — Tyger Pines in District 6 and The Trailer Park in District 2 — are seeking more time on their zoning permits through the consent agenda.

    What it means: The applicants seeking added time to pursue their approved projects.

    Follow this issue →
  • 2910 E. Main Street developments

    Two projects at the same East Main Street address — a commercial subdivision and a townhome development — are up for commission action in District 3. Whatever the commission decides shapes retail and housing growth along that corridor.

    What it means: East Main Street property owners and future shoppers and townhome residents if the projects advance.

    Follow this issue →
  • Development Agreements for Numara, LLC and Valara Holdings, LLC

    Three major data center agreements advanced on second reading despite hours of resident testimony about noise, water, blank contract pages and enforceability. These deals lock in terms for years and could shape the county's tax base, power grid demands and quality of life near the sites.

    What it means: The county gains new tax base and jobs, local vendors and workers benefit, and school and workforce programs receive community fund money — while residents near the sites gain contractual guardrails.

    Follow this issue →

Published by South Carolina Record. 2 meetings covered.