Wastewater Treatment Plant 2 Upgrades
Summary
TCUD's plan focuses on trenchless sewer pipe rehab, manhole lining, lift station upgrades, and bypass pumps for critical stations. The department requested $1.5 million in state appropriations for about three miles of cured-in-place pipe, and can't apply for more grants until the wastewater plant project closes.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Jun 15, 2026.
Impact analysis
Funded by utility fees, not taxes; $200,000/year buys roughly half a mile of pipe rehab without grant money.
Every water and sewer customer — proactive rehab cuts treatment costs and reduces the risk of failures and boil-water advisories.
Mentions & discussions (2)
City Council - Jun 15, 2026
The upgraded Plant 2 is expected to start up the second week of July, after which work shifts to Plant 3. Stage 2 drought restrictions remain in effect — residents are urged to cut back irrigation.
City Council - Mar 31, 2026
TCUD's plan focuses on trenchless sewer pipe rehab, manhole lining, lift station upgrades, and bypass pumps for critical stations. The department requested $1.5 million in state appropriations for about three miles of cured-in-place pipe, and can't apply for more grants until the wastewater plant project closes.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Tega Cay
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.