Civic Issues
Topics getting the most attention in Lexington public meetings, ranked by how frequently they are discussed.
9 issues in water utilities
Sewer Hydraulic Model
The town is moving forward with a sewer hydraulic model to plan future wastewater capacity — informational only at this meeting.
Massive sewer and water capital investment program
The town is moving forward with a sewer hydraulic model to plan future wastewater capacity — informational only at this meeting.
Cross-connection control program protections
Final approval of ordinance updates that keep town code in step with the new water protection program, guarding drinking water from backflow contamination.
Windstream/Kinetic Fiberoptic Franchise Agreement
The new franchise agreement sets consistent terms for fiber providers in town, matching prior deals with Ripple Fiber and Lumos, and gives the town oversight of construction and installation work. First reading passed; more readings remain.
FY 2027 Enterprise Fund Budget and future utility rates
Operating costs are rising about 9% a year while revenues grow less than 3%, so the Town is budgeting for a rate study — its first in about six years — that will likely recommend rate increases. No increase is planned for the current year.
West Columbia water litigation
Council quietly approved hiring the Smith Robinson law firm for the town's water litigation with West Columbia after executive session.
14 Mile Creek Gravity Trunk Sewer Project
The town's sewer system is getting major attention: upgrades to the Mill Stream Station that handles 90–95% of sewer flow, hydraulic modeling, and system-wide inspections. Long-term, the town must expand sewer treatment capacity in Cayce, and a Professional Engineering Report will define scope and costs.
Undergrounding downtown power lines
Councilmember Gavin Smith wants staff to explore whether the town can require Dominion to bury power lines in key corridors like Main Street. Preliminary estimates say it would be very expensive, and it's unclear whether the Public Service Commission gives the town the authority.
Sewer infrastructure and Cayce treatment expansion
After a sanitary sewer overflow reported in The State newspaper, the Utilities Department is adding a hydraulic model, upgrading the Mill Stream station that handles 90–95% of flow, and doing sonar and camera inspections to find weak spots before they fail.